Solihull Community Fire Station

Company Information: 

Watson and Cox (Construction) Ltd. has developed a long established reputation and regional expertise since its formation over 35 years ago. From their base in Wellingborough, they have delivered and developed a portfolio of projects in both public and private sectors across a wide range of industries and markets. These include Industrial, Commercial, Retail, Education, Residential, Leisure and Health Care

Watson & Cox Construction Ltd.
Brunal Close, Park Farm,
Wellingborough, Northants
NN8 6QX

Telephone: 01933 677777

Fax: 01933 400219

 

 

Project information

The Solihull Community Fire Station project started in August 2010 and completed in March 2011. It was a refurbishment project to a masonry/brick and block frame construction representing a floor area of approximately 1740m2. The project had plenty of scope for waste minimisation techniques to be identified at the pre construction phase site waste management plan (SWMP). Watson and Cox Ltd enlisted the assistance of Waste Plan Solutions Ltd, to help them integrate the SWMP onto all of their projects.

The Approach taken

Numerous waste minimisation decisions were undertaken successfully during the construction phase SWMP including;

• To ensure that the removal of existing materials was carried out in an economic manner and where possible, limit excessive damage
• The use of mechanical cutting techniques for the building engineering services, to ensure reduced waste
• To reduce timber waste by reuse of pallets through procurement
• To utilise tape/joint finishes instead of plastering, to reduce excessive waste
• To segregate waste arisings on site.

Achievements

The targets set in the SWMP were to reduce waste by 10%, to recycle 70% and to send 20% to landfill, this target was easily achieved. The original forecast for inert waste was 339 tonnes, but no inert waste was sent from site during the construction phase and non hazardous waste was a mere 114 tonnes, which for a project cost of £1,037,007 and the floor area is impressive. Any mixed waste that left site easily achieved the target recycling rate through the assistance of their waste contractors.

Cost savings

Skip costs were high at tender stage based on the estimated quantities of waste that would be produced. This meant that a cost saving of £30,256 has been achieved through waste minimisation techniques implemented on site. This cost saving equates to 3% of the total project costs.

Lessons Learnt

Segregated waste skips will always be considered for future projects as they reduce the waste disposal costs and only waste contractors will be used with high offsite recycling rates to ensure best practice and reduction of waste to landfill.

Watson and Cox Ltd plan to develop their own in house forecasting data, assisted by Waste Plan Solutions to ensure that the pre construction plan aligns as closely as possible to actual waste
arisings data.
The procurement strategy will be addressed shortly which will include; sustainable products, returnable
packaging schemes and sub contractors procurement.

In conclusion

Watson and Cox Ltd are delighted with the integration of SWMPs onto their sites and will continue to strive to achieve their target of 5% project savings through SWMPs. There are further areas of potential savings they would like to continue to address through the assistance of Waste Plan Solutions Ltd.
 

Since the introduction of the SWMP Regulations 2008 our organization has strived to embrace not only the legislative requirements but also the underlying ethos. In embarking on a partnered approach with Waste Plan Solutions Ltd we have benefited from their extensive experience and successfully managed to develop and implement systems to comply with the Regulation requirements and also to contribute positively to best practice operations resulting in significant project cost reductions.

Support from Waste Plan solutions Ltd has been tailored to our business needs and provided with considerable knowledge consistently delivered in an enthusiastic and professional manner. Without such support we undoubtedly would have encountered greater difficulty in achieving our aims, passed over the commercial benefits and would not have received commendations from the Environment Agency for our approach and level of implementation,

Watson and Cox - D Wallace Construction Director
T: 01604 859961, M: 07788 141515,
info@wasteplansolutions.co.uk

Registered in England No. 7002484.
Registered Office. 17 Whitegates, West Hunsbury, Northampton NN4 9XA
VAT no. 118373024
Web Design by 1PCS© Waste Plan Solutions 2010 (Site Waste Management Plans - SWMP)